Actual unit for June has to be 209. But the unit for which reading was taken earlier (April & May) was not deducted from the ongoing reading and hence it shoots up to 435
| Bill No | Ongiong Reading | Previous Reading | Reading Date | Unit | Amt |
| 679582028 | 192 | 81 | 20-Jan-20 | 111 | 770 |
| 719526540 | 314 | 192 | 19-Feb-20 | 122 | 900 |
| 743674745 | 435 | 314 | 19-Mar-20 | 121 | 910 |
| 773786987 | Not available | 435 | NA | 118 | 700 |
| 804022742 | Not available | 435 | NA | 118 | 880 |
| 839664342 | 880 | 435 | 20-Jun-20 | 445 | 1740 |